This article investigates planning practice concepts used to deal with the most important factor influencing the pace of urban development: land value. At the time of urban development, officials and planners are directed to tools such as changing land use and offering compensation to landowners to facilitate the development project.
Land use is influenced by many urban characteristics, such as urban densities and transport nodes and networks. Changing one of these elements in the development process directly affects the others, and vice versa.
US context: The framework used in this article comes from an American source: Kaiser, Godschalk and Chapin’s Urban Land Use Planning was published in the US, and the values it describes apply on both sides of the Atlantic. What differs is who controls land use. In the UK, the right to develop land was brought under public control by the Town and Country Planning Act 1947, and local authorities decide applications against a development plan. In the US there is no national land use system. Land use is a state power delegated to cities and counties, which exercise it mainly through zoning. The federal government influences it only indirectly, through funding, environmental law and the constitutional protection of private property. The same land value problem is therefore handled with different tools, as the following sections show.
Land value and land use change
To have a clear idea of how land changes in value, Edward J. Kaiser (1) identifies three factors that determine land value. Social value is the value people see in the land in terms of desired patterns of use and social aspiration. Market value is the value people see in land as a real estate commodity. Ecological value is the weight people give to the natural system and to ways of mitigating environmental threats.
Various problems cause a change in one of these factors, and accordingly land use changes, so planners are required to deal with the change to minimize any negative effect on urban development. For example, the nature of a land function changes, causing either a shift of that function or a modification of land uses.
River banks and waterfronts in many cities of the world are very precious parts of city land. They combine the three factors that specify value: social, market and ecological. These locations are attractive for luxury residential development, commercial uses, open urban space for public use, and marine civic activity.
The Thames case
Between 1960 and 1990 the River Thames (2) went through a big land use change because, as mentioned earlier, the nature of land use functions changed. Industrial, commercial and public facilities were aligned along the river bank. Heavy shipbuilding, which requires deep water that the river could no longer provide, shifted to Essex. Some heavy industrial functions preferred to move to green field areas close to resources. Public facilities that used water in operations, and materials such as the coal used to produce electricity and carried by ships on the river, were cleared to other locations, because water was no longer the means of transporting materials and other places provided a good source of water. See Figure 1.

These changes in the nature of land uses came to the planners’ attention after many environmental, health, transport and congestion problems.
Global economic restructuring, and the shift of industry towards the service sector, changed London’s economic function towards finance, tourism, consumer services and information technology. The urban riverside saw an increase in office space built along the river, taking advantage of the property boom of the 1970s and early 1980s. This was a clear change of land use from industry to a clean function, office space, on land left vacant by the industries that had moved.
Planning activities such as the gentrification of river banks, more open space and better access to the area led to the introduction of residential land uses. Planners, policymakers and officials directed development towards this type of land use because of the increase in development revenue, especially since the land is under government control. Very little open and green space was kept or introduced near and along the river bank, because of limited revenue and the lack of alternative places in the city. See Figure 2.

Land use change on the Thames river bank was caused either by improper planning or by the types of land use that needed to be attached to the river for transport and for water use in industry.
One can argue that there was improper planning, because public facilities that used water for operations could have been located at the seaside of London and still had access to the city by the river. Chemical and other industries that use water for transport could also have been located near the seaside. The labour and staff working in these industries could have lived near their work and still had access to the city. See Figure 3.

US context: American waterfronts followed the same sequence. After the 1950s, containerised shipping needed deep water and large areas of flat land, so cargo handling moved from the Manhattan and Brooklyn piers to Port Newark-Elizabeth in New Jersey, much as London’s heavy shipping moved downriver. The old industrial riverfronts were left vacant. Two well-known responses show how public bodies organised the change. Battery Park City in New York was built on landfill and is owned by a state public-benefit corporation, which leases the land to developers. Baltimore’s Inner Harbor was redeveloped through a long public-private programme that began in the 1960s, led by the city with public funds from several levels of government.
London’s Docklands were also redeveloped by a government-appointed body, the London Docklands Development Corporation (1981). In practice the two countries ended up closer than their legal systems suggest: where land values changed sharply, the public sector took the lead in assembling land and funding infrastructure.
Zoning and free-form planning
Planners in the UK have generally avoided rigid zoning of land use. Segregating uses such as residential, commercial, industrial and farmland is costly, because it requires a very developed transport system and services system. This type of planning, which depends on a fixed blueprint, is still used in some parts of the Middle East. Critics of zoning point to increased social segregation, increased crime, decreased land value, and the high cost of building the services and transport systems it requires. For that reason London has followed a free-form planning approach, whose policies and methods have changed several times since the early twentieth century.
Land use change must consider the direct relationship between land use, urban densities, and the size and network of transport nodes.
Zoning in a development plan produced by planners can be applied either to newly vacant land or to developed land. In the UK zoning is not preferred, presumably because of the problem of compensation and betterment in the tax system. That is one way to avoid the government paying money to owners. For more on how UK local plans are made, see my article Rethinking Local Development Plan-Making: An Alternative Approach Based on Lessons from the EU Plans.
US context: The United States took the opposite route. New York adopted the first comprehensive zoning resolution in 1916, and in Village of Euclid v. Ambler Realty (1926) the Supreme Court upheld zoning as a valid use of the police power. Today almost every US city divides its land into districts with rules on use, height and density. A project that complies is permitted ‘as of right’, which gives developers the certainty the UK system lacks: the zoning map shows what can be built and, roughly, what the land is worth. Houston is the best-known exception, relying on covenants and other regulations instead.
US practice has also moved towards flexibility. Planned unit developments, overlay and floating zones, special permits and variances turn strict zoning into something closer to the negotiated UK approach. The criticisms of zoning made above are also made in the US, where single-family-only zoning has been linked to segregation by race and income and to housing shortages, and where several states and cities have recently reduced it.
Compensation and betterment
What are compensation and betterment? Peter Penny (3) defines betterment as any increase in the value of land or property due to community cause or public sector development. Betterment can come in three types: recoupment, set-off and direct charges. I can simplify the concept as the distribution of charges on plot owners who have received an increase in the value of their land or property due to public work, such as constructing a new road. The charges should not exceed the amount of value received by the owners. Compensation is the money paid to owners when their properties are damaged by public work or development, or when their property or land is taken over by the public sector or a developer. Compensation can arise when there is rezoning or zoning for an area of land. These two actions in planning are still under debate in urban planning circles.
US context: In the UK, refusing planning permission generally attracts no compensation, because the right to develop was brought under public control in 1947. Compensation arises mainly when land is compulsorily purchased or when a permission already granted is withdrawn. In the US, compensation rests on the Fifth Amendment, which forbids taking private property for public use without just compensation, and two situations must be distinguished.
First, when government acquires land by eminent domain it pays fair market value. Kelo v. City of New London (2005) confirmed that ‘public use’ can include economic redevelopment, which caused a strong political reaction and new limits in many states.
Second, when regulation reduces land value without taking the land, the owner is generally not compensated. Courts treat it as a ‘regulatory taking’ only in limited cases: when regulation removes all economically beneficial use of the land (Lucas v. South Carolina Coastal Council, 1992), or, under the balancing test of Penn Central v. New York City (1978), when its economic impact and its interference with investment-backed expectations are severe. A rezoning that lowers value is therefore usually not compensated. Some states went further: Oregon’s Measure 37 (2004) required compensation or a waiver of the rules, and was narrowed by Measure 49 (2007) because of its cost and its effect on planning.
US context: The betterment idea has a clear US counterpart, the special assessment: owners of land near a new road, sewer or park are charged part of the cost, normally capped at the benefit received, which matches the limit described above. Other value capture tools include impact fees and exactions (the developer pays or provides land or infrastructure as a condition of approval), tax increment financing (TIF), where future growth in property tax from a redevelopment area repays the public investment, and density bonuses, where extra development rights are traded for public benefit. Courts limit these tools: Nollan v. California Coastal Commission (1987) and Dolan v. City of Tigard (1994) require a link and ‘rough proportionality’ between the condition and the project’s impact, and Sheetz v. County of El Dorado (2024) applied the same test to fees set by legislation. The UK equivalents are Section 106 agreements and the Community Infrastructure Levy, which replaced earlier betterment taxes.
Osborn (4) presents in his book many obstacles to, and views on, applying the concept of compensation and betterment. For example, how can planners define which lands have received betterment and which must receive compensation? How should the value of betterment and compensation be decided? If zoning occurs, it is hard to decide or investigate which lands lose value because of the uncertainty of planning permission. And Osborn says an important issue is how to obtain the funds for betterment and compensation.
Ideas to tackle the problem
Officials and planners have introduced many ideas to tackle this problem. The first is pooling of ownership. Here the authority compulsorily buys the land and buildings of an area for redevelopment and prepares a development plan. It executes the plan and resells all the land and buildings to the former owners, taking the owners’ previous property values into account. Alternatively, the authority does not buy the land but makes a development plan and re-divides the plots accordingly. The owners then receive land in the new arrangement equivalent to their previous land value.
Another idea is permanent ownership pooling. Here the authority takes over the whole town, or part of it, for development with infrastructure. A development company is established, and the landowners become shareholders (by the amount of their land value) and receive part of the public transport revenue. In this idea betterment and compensation do not exist.
The third idea is purchase of all the land by the municipality: municipal land ownership. It applies when there is a plan to redevelop old areas completely, and betterment and compensation disappear totally. Stockholm’s Hammarby Sjöstad, discussed in my article Managing a Development in Practice, is an example of a municipality-led development.
US context: Land readjustment of the first kind is routine in continental Europe (for example Germany’s Umlegung) but rare in the US, where strong property protection makes forced re-division of plots politically difficult. US authorities instead assemble land through eminent domain, as in the urban renewal programmes upheld in Berman v. Parker (1954), or through public development corporations. The third idea has a close US example in Battery Park City, where a public authority owns the land and leases it to developers on long ground leases, so that the increase in land value stays with the public sector. Community land trusts apply a similar logic at small scale, keeping land in permanent non-profit ownership.
Discussion
Several issues can be raised about the debate on land use change and the concept of betterment and compensation:
- Land use change comes into action when there is no zoning in urban planning. In all cases planners will not allow industrial land use adjacent to housing or residential land use. Here land value is defined by the existing land uses and market conditions, supply and demand. Restructuring land uses for a whole area will not create any land use change or value problems.
- EU countries suffer from land use change because of the financial burden on government funds. Changing land use affects road networks and public transport networks such as buses, trams, trains and metro, which affects the layout of area development. Continuous land use change requires revisiting the design of the road and public transport networks to define the new requirements: new roads, increased size, and maybe a new metro station.
- Free-form land use planning, as in the UK, still relies on the suitability of land uses and groups. Land use planners conduct land suitability assessments for development when preparing a development plan. Here planners are still doing zoning, but in free form and subject to change at any time.
- In free-form planning, the redevelopment of an area should be phased. The authorities then do not worry about preparing funds, except for the parts currently subject to development, such as residential buildings. Owners are not forced to sell their land or property, but are encouraged to redevelop it as per the main development plan, financed privately or with loans from banks or investors. I discuss government-assisted private sector development as a funding approach in Part 5 of my Local Development Plan series.
- In my view, betterment and compensation is a naive concept that is hard to apply in reality. Tax systems undermine the idea, because the government takes control of development and is forced to pay for funding it. In many Middle Eastern countries, and perhaps in Asia also, any owner whose land is part of a redevelopment or new development is compensated if the land is taken. The idea of betterment does not exist there, as the government’s duty is to provide services for new and redeveloped areas, and landowners are obliged to pay for the installation of and connection to services when they decide to build, which covers the expenses.
- In my view, zoning is a great idea in preparing for development, for various reasons. There is no real loss in the variety of uses: industrial land will generate income equivalent to its use and value in the long run, while residential land use has direct, short-run, high benefits compared with industrial land use. Zoning helps governments predict the number of services required for an area and fix them in a funding plan. It determines the road network and the public transport required to eliminate congestion, and defines clearly what type of public transport will be required in the future (trams, trains, metro) in terms of size and location. The developer knows exactly the allowable densities, which removes the uncertainty of planning permission and defines the development revenue. Land value is clear, based on the land uses specified for the area.
- In Middle Eastern countries, areas can be removed after a certain length of time, for example fifty years after development. This way the government does not carry the financial burden of purchasing land for redevelopment, because the land and the property are already within the time limit for demolition. The value of the property also plays a part: a house built more than fifty years ago has depreciated to little or no value, so the price is the value of the land only, and the part on top of the land is neglected when the property is sold. The owner is therefore usually willing to sell, and the government pays for the land, not for a building that no longer has value.
Comparing the two systems
The comparison below summarises the points made above. The US experience supports part of the argument in the discussion: zoning gives certainty, but a purely rule-based system still needs flexibility and ways of sharing the value that public decisions create. The UK experience shows the opposite: discretion keeps flexibility, but leaves compensation and betterment unresolved. The UK’s betterment taxes were introduced and abolished by governments of different parties; for the wider political context, see my article Politics of Urban Planning: Ideologies, Reforms and Outcomes: The UK Parties Case.
| UK (the article’s case) | United States | |
| Who controls land use | National framework; local authorities decide applications against a development plan. | State power delegated to cities and counties; federal role is indirect. |
| Planning approach | Discretionary: each application is decided on its merits (‘free form’). | Rule-based zoning, with flexible tools (PUDs, overlays, variances, special permits). |
| Certainty for developers | Lower: permission is uncertain until granted. | Higher where a project complies with zoning as of right; lower where rezoning or discretionary approval is needed. |
| Compensation for lost value | Generally none when permission is refused; paid for compulsory purchase and for withdrawn permissions. | None for most regulation; required for eminent domain and for regulatory ‘takings’ (Penn Central, Lucas). |
| Betterment / value capture | Betterment taxes (1947, 1967, 1976) were abandoned; today Section 106 and CIL. | Special assessments, impact fees, exactions, TIF, density bonuses; limited by Nollan, Dolan and Sheetz. |
| Land assembly | Compulsory purchase; public bodies such as the LDDC. | Eminent domain (Berman, Kelo), public development corporations, ground leases (Battery Park City). |
| Waterfront example | Thames-side, Nine Elms, Docklands. | Battery Park City (New York), Inner Harbor (Baltimore). |
References
1. Kaiser, E., Godschalk, D. and Chapin, F., 1995. Urban land use planning. Urbana: University of Illinois Press.
2. LPAC/LRA, 1992. Land use change and policy on the Thames-side 1967-1991. London: London Rivers Association / London Planning Advisory Committee.
3. Penny, P., 1966. The compensation and betterment problem in town planning. The South African Journal of Economics, 34(4), pp.257-269.
4. Osborn, F., 1942. The land and planning. London: Faber and Faber.
5. Talib, H., 2017. The evolution of land use policy in central London. M.A. dissertation, University of Liverpool.
6. Uthwatt Committee, 1942. Final report of the Expert Committee on Compensation and Betterment, Cmd 6386. London: HMSO.
7. Town and Country Planning Act 1947. London: HMSO.
8. Village of Euclid v. Ambler Realty Co., 272 U.S. 365 (1926).
9. Penn Central Transportation Co. v. New York City, 438 U.S. 104 (1978).
10. Lucas v. South Carolina Coastal Council, 505 U.S. 1003 (1992).
11. Nollan v. California Coastal Commission, 483 U.S. 825 (1987).
12. Dolan v. City of Tigard, 512 U.S. 374 (1994).
13. Kelo v. City of New London, 545 U.S. 469 (2005).
14. Sheetz v. County of El Dorado, 601 U.S. 267 (2024).
15. Berman v. Parker, 348 U.S. 26 (1954).